Nigeria’s national grid was generating 3,743 megawatts around midnight and 3,179 MW by 6 a.m., according to readings checked by The Guardian Nigeria. By 6 p.m., generation was still about 3,180 MW. The newspaper reported the figures on November 19, describing the readings as the previous day’s. The roughly 15% fall measures power output over six hours.
At 6:28 p.m. on November 18, the independent system operator’s distribution profile put the combined allocation to eleven distributors at 2,885 MW. Abuja received 551 MW, the largest share. Ikeja received 366 MW, Ibadan 340 MW and Eko 339 MW. Yola received 74 MW. Generation measures national output at a point in time. The allocations are the power assigned to distributors. They do not tell customers how many hours of service their homes received.
The operator had cited two constraints on November 5: reduced gas supply to thermal plants and lower water inflows to hydroelectric reservoirs. NNPC Limited, the national oil company, replied on November 7 that its pipelines were available. Its statement distinguishes a working pipeline from gas contracted, delivered and taken by a plant. It called for figures on deliveries, maintenance and generating units before assigning responsibility.
Hydropower accounted for 32.66% of grid electricity in 2025, The Punch reported from the electricity regulator’s annual figures. Energy professor Dayo Ayoade told the newspaper that low reservoir levels and unreliable gas could deepen shortages. Yemi Oke of the University of Lagos said steady gas could sustain generation through the dry season, while distributors facing a shortfall could give priority to customers on higher tariffs.
That last question is already before lawmakers. The Guardian reported that members of the House power-sector reform committee expected to present their findings the following week, after a debate about customer tariff bands and whether distributors deliver the service those tariffs promise.
What the evidence cannot tell us
- Grid figures are snapshots, rather than a daily average. The allocation cannot establish losses, hours of service or the number of homes without power.
- The operator’s account and NNPC’s response concern different parts of the supply chain. The underlying plant-by-plant fuel data were unavailable.
What to watch
Watch the next operator readings, data on gas actually reaching power stations, and the House committee’s findings on tariffs and service commitments.
Read the sources. Credit the work.
The reporting and documents behind this brief, linked directly to the source. Verified publisher and author credits appear where available; other entries show their actual website address. Several links may draw on the same underlying reporting or research.
The Guardian Nigeria
Power generation drops to 3,180MW as DisCos ration supply (opens in a new tab)guardian.ng · November 19, 2026
Reporting / analysisContent read for this publication · November 22, 2026Publisher and byline credit checked November 22, 2026. View credit on the source page (opens in a new tab).
NNPC Limited
NNPC confirms gas supply and network availability (opens in a new tab)nnpc-web-customer-prod.azurewebsites.net · November 7, 2026
Primary document / sourceContent read for this publication · November 22, 2026Publisher and byline credit checked November 22, 2026. View credit on the source page (opens in a new tab).
The Punch
Dry season: Fear mounts over worsening power crisis (opens in a new tab)punchng.com · November 22, 2026
Reporting / analysisContent read for this publication · November 22, 2026Publisher and byline credit checked November 22, 2026. View credit on the source page (opens in a new tab).
This story was written and checked using AI against the linked evidence. No routine human review is claimed. Read the method.
Suggest an update or correctionPublished corrections